Find the ground
Screen real parcels, flood and wetland constraints, zoning, access and expansion rights.
New Orleans East / from November 2026
SoLo is studying a 15–25-acre first campus for creative manufacturing, a small semiconductor process study, solar and agriculture, and its AI operations. DoLo REI would lead site diligence. The larger campus image shows the long-term vision.

The right-sized first move
The new phasing plan replaces the earlier 150-acre first-site concept. It studies adjacent options for a later 50–100-acre footprint. None of these parcels has been selected or acquired.
Screen real parcels, flood and wetland constraints, zoning, access and expansion rights.
Test supply, apparel and publishing lines with customers, equipment quotes and unit economics.
Study a 5,000–8,000 sq ft initial process area only after product, utility and safety feasibility.
Test the proposed 2 MW solar and under-panel crop concept against a real parcel and utility response.

Phase 1 / the practical sequence
The factory line must show buyers and workable margins. A parcel must clear land, flood, environmental and utility checks. The cleanroom and foundry stay in the feasibility or later-phase lane until qualified engineering and capital support them.
See the decision gatesVisual roadmap / November 2026 onward
These are overlapping planning windows, not promised dates. Groundbreaking means permitted work on a secured site with financing and a contractor in place; it does not mean a fab is producing chips.
Prove one buyer need; shortlist three 15–25-acre parcels.
Gate: Buyer signal + site listCheck zoning, flood, wetlands, title and expansion rights.
Gate: One viable parcelGet survey, geotech, utility response and costed design.
Gate: Qualified design + quotesDocument offtake, site control, funding and cash needs.
Gate: Signed evidenceComplete required city, utility and environmental reviews.
Gate: Approvals + conditionsStart permitted site work with land, funding and contractor.
Gate: Notice to proceedWorking range: 18–36+ months for a first permitted pod if the gates clear. No groundbreaking date is announced.
Download visual roadmap (SVG)Capital model / preliminary
The founder-supplied Capital Cost Analysis totals nine proposed land, site, building, equipment, power and utility cost lines. The arithmetic checks, but the inputs have no parcel, dated vendor quotes, utility study, buyer contracts or financing terms behind them yet.
This figure is an unquoted, unaudited planning scenario. It is not the Phase 0 fundraising goal, committed capital or a construction bid.
What comes next
Commission a costed Phase 0 feasibility scope, then update the estimate using actual site conditions, engineering, supplier quotes and a realistic contingency.
See the separate Phase 0 tallyPhase 0 / feasibility funding
The first funding target will come from real quotes for parcel due diligence, survey, engineering, utilities and commercial validation. The public tally starts at the founder-reported amount below; it does not count unverified pledges.
Discuss backing Phase 0Public fundraising tally
Founder-reported starting total · No public receipts posted
Goal: pending a quote-backed Phase 0 budget
As of November 6, 2026
How we check the ground truth
Site zoning: New Orleans Property Viewer. Flood maps: FEMA Map Service Center. Wetlands: U.S. Army Corps New Orleans District. Utility requests: Entergy connection requirements. Environmental permits: Louisiana DEQ. Construction: New Orleans new-construction permit.